Auburn fire panel approves $264,946 change order for site work
Auburn fire station panel approves $264,946 in change orders, weighs $450,000 fix for a bay too narrow for truck jacks.
Other Committee · Meeting of September 15, 2026
Auburn fire station panel approves $264,946 in change orders, weighs $450,000 fix for a bay too narrow for truck jacks. The Fire Station Building Committee unanimously approved a $230,430.92 payment for final underground ledge removal and a $34,515 site-work package linking the station's parking lot to an adjacent park and the neighboring Dunkin' Donuts lot, for a combined $264,945.92. Members also approved Pay Requisition No. 4 for $1,041,954.71, with the project reported at 15.57 percent complete.
The Fire Chief and a presenter identified as Glenn told the committee that earlier value-engineering cuts, which trimmed 950 square feet and saved more than $700,000, narrowed the mechanic's bay to about 18 feet, leaving no room for the originally planned truck jacks and no way to lift the department's ladder truck. A proposed in-ground lift system, priced at roughly $270,000 for the units alone, carries a working estimate "not to exceed $450,000." One member invoked the project's $4.2 million in bid savings, warning against "the $3,000 decision in 1964 not to upgrade the steel." No vote was taken because the item was not on the agenda.
In the full story:
- Who Was There
- Organizations And Documents Referenced
- The complete report — 2,622 words
Source: the Other Committee meeting of September 15, 2026, reported from the official video recording and transcript.
Members read the rest of this story and every Worcester County meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this story
Know someone in Worcester County who follows town government? Share Townbrief Worcester County: they can sign up free.